Production planning plays a very important role in bakery . Its main objective is to plan production of various SKU s in advance so as to enable each part of production to be ready when actual production is schedule . Production plan are made generally for a month and further broken down to weekly and daily production plan . Production plan also helps in getting product with optimum cost . Big bakeries with multi locational presence have centralized production plan made and which are then synchronised with individual plants at local levels .Production planning help companies to avoid any sale loss due to un availability of product .In most of the large bakeries PPC ( Production Planning & Control ) takes help of ERP software to plan production .
Sales forecast
PPC deptt collects the sales forecast from sales deptt and plan s production keeping into following factors in mind. Normally a pattern is set for various SKUS demand with few special orders such as Promos or special orders from big customer s.
Production plans are made with these critical factors
Material requirement planning
Once sales forecast are available PPC deptt issues material requisition to purchase deptt for sourcing of ingredients , packaging and some cases machine spare parts .Lead time plays important role hence material having longer lead time needs to be procured in larger volume .Also one needs to check the stock s in hand while ordering .
Plant loading
PPC deptt then plan the optimum loading of plants with keeping in view the plant efficiency /capacities and availability . Production plan helps engineering deptt to take any modification or repair in advance to meet the schedule .
Change Overs
Normally change overs are avoided but for demand from market PPC has to plan change overs with minimum loss of time and loss to production .
Manpower
Manpower requirement are spelt out in advance with help of production plan so that in case of increase in number the HR deptt arrange the numbers in advance or inversely if decrease in requirement of worker the labor contractors are notified in advance. Weekly offs to be scheduled as per production plan .
Dispatch
Once the production plan is made the logistics deptt arrange for the container accordingly and the containers are ready at the time of production and documentation done without delays.
Even after careful production planning there might be changes in production plan for which there should be a secondary plan which can be taken without significant loss to the company . Main Reasons are listed
1 Stock out situation for raw material/packaging
2 Break down of machinery
3 Non availability of labour
4 Cancellation of Order
5 Situation like strikes / government orders / Break down in Utilities such as electricity /water supply .
6 Transport Problem
PPC deptt acts as the centre of all activity related to factory operations hence it should be alert and keep a tab on developments of internal and external factors affecting factory operations .
Sales forecast
PPC deptt collects the sales forecast from sales deptt and plan s production keeping into following factors in mind. Normally a pattern is set for various SKUS demand with few special orders such as Promos or special orders from big customer s.
Production plans are made with these critical factors
- Availability of material
- Availability of manpower
- Availability of plant and machinery
- Dispatch plan
- Festivals packs and promotions planning in advance
Material requirement planning
Once sales forecast are available PPC deptt issues material requisition to purchase deptt for sourcing of ingredients , packaging and some cases machine spare parts .Lead time plays important role hence material having longer lead time needs to be procured in larger volume .Also one needs to check the stock s in hand while ordering .
Plant loading
PPC deptt then plan the optimum loading of plants with keeping in view the plant efficiency /capacities and availability . Production plan helps engineering deptt to take any modification or repair in advance to meet the schedule .
Change Overs
Normally change overs are avoided but for demand from market PPC has to plan change overs with minimum loss of time and loss to production .
Manpower
Manpower requirement are spelt out in advance with help of production plan so that in case of increase in number the HR deptt arrange the numbers in advance or inversely if decrease in requirement of worker the labor contractors are notified in advance. Weekly offs to be scheduled as per production plan .
Dispatch
Once the production plan is made the logistics deptt arrange for the container accordingly and the containers are ready at the time of production and documentation done without delays.
Even after careful production planning there might be changes in production plan for which there should be a secondary plan which can be taken without significant loss to the company . Main Reasons are listed
1 Stock out situation for raw material/packaging
2 Break down of machinery
3 Non availability of labour
4 Cancellation of Order
5 Situation like strikes / government orders / Break down in Utilities such as electricity /water supply .
6 Transport Problem
PPC deptt acts as the centre of all activity related to factory operations hence it should be alert and keep a tab on developments of internal and external factors affecting factory operations .